INSTALLATION and cure timeline

INSTALLATION TIME

  • Installation times are typically between 1-2 days, but vary depending on the scope of the project and the external Colorado temperatures.

CURING PROCESS

  • The coating requires 24hrs/48rs of cure time depending on temperature. We recommend opening garage windows or your garage doors as much as possible to allow ventilation and airflow.

24 HOURS

  • After 24hrs of cure time, the floor is ready for foot traffic and lighter garage items such as bikes, trashcans or boxes. (Add 24hrs if night-time temperatures drop below 15°F.)

48 HOURS

  • After 48 hours a vehicle can be driven on the floor. Heavier, wheeled items can also be brought back into the garage. Heavy items NOT on wheels can be lifted and placed back into the garage. Avoid dragging heavy non-wheeled objects on the floor for a full seven days. (Add 24hrs if night-time temperatures drop below 15°F.)

1 WEEK

  • Heavier items that do not have wheels can be pushed or pulled across the floor at this time.